Maintenance
Emergency Hardware Maintenance
Resolved Mar 22 at 11:00am EDT
All services are unavailable as our provider performs emergency maintenance on our Miami servers. This issue is related to our internal systems. Downtime should be short-lived.
Hardware Server Power Maintenance
Resolved Mar 26 at 06:00am EDT
All Faraday services will undergo mandatory maintenance to upgrade the power lines from our cabinet in the Miami Datacenter (MI1). The purpose of the maintenance is to add more power capacity to the cabinet by replacing the power lines and PDUs one-by-one following the below schedule:
Start of Planned Work Window: LOCAL: TUESDAY, 26 MARCH 2024, 06:00 / UTC: TUESDAY, 26 MARCH 2024, 10:00
End of Planned Work Window: LOCAL: TUESDAY, 26 MARCH 2024 07:00 / UTC: TUESDAY, 26 MARCH 2024, 11:00
...